Dřísy, Czech Republic, 2025

Implementation:

  • 11 weeks

  • Output: 2.4 MW

  • Number of panels: 3,400

  • Number of ground screws: 780

A 2.4 MW photovoltaic power plant was completed in the Polabská lowlands within 11 weeks. This is another power plant that uses our efficient East-West design.