Maryan, Bulgaria, 2024

Implementation:

  • Start of construction: 1.7.2024

  • Completion: 20.7.2024

  • Output: 1.2 MW

  • 2.100 Panels

  • 808 screws

In July 2024, our next successful project in Bulgaria was launched - the Maryan PV plant in the Elena Mountains. The 1.2 MW power plant in challenging geological conditions was fully completed in 19 days, including the installation of the drills.